Reagan National Airport Hangars 2 & 3 Roof Replacement

Roof replacement design for two aircraft hangars at Ronald Reagan Washington National Airport, updated in 2025 to current wind and energy codes. The project is being rebid, with construction expected to start in spring 2027.

Reagan National Airport Hangars 2 & 3 Roof Replacement

Overview

As a subconsultant to PGAL, REI designed the replacement of the deteriorated Hypalon (CSPE) roofing on the upper and lower roofs of Hangars 2 and 3 at Ronald Reagan Washington National Airport for the Metropolitan Washington Airports Authority. REI surveyed the roofs with test cuts and completed the original design in 2019. In 2025 REI revisited the site and updated the design from the 2015 to the 2021 building codes, including ASCE 7-22 wind pressures. The project is currently being rebid, and construction is expected to start in spring 2027.


Scope of Work

  • Surveyed the upper (metal deck) and lower (concrete deck) roofs with test cuts, documenting drains, penetrations and abandoned rooftop equipment

  • Prepared construction documents and specifications for TPO roofing over R-30 polyiso insulation, with tapered insulation at dead-level areas

  • Specified a vapor retarder over the upper-roof metal deck, since the unconditioned hangars are often open to outside air

  • Prepared a code analysis updating the design to the 2021 IBC and Virginia Construction Code, including wind uplift plans and parapet redesign

  • Detailed new through-wall flashing in the clay tile masonry walls above the lower roofs

  • Will provide construction administration, including shop drawing reviews


Results

  • Brought a 2019 design up to current codes, including substantially higher ASCE 7-22 wind uplift pressures, so the project could proceed to permit in 2026

  • Sequenced clay tile removal for the through-wall flashing in short sections, so no temporary structural bracing is required

  • Protected the new insulation from condensation in hangars that are unconditioned and often open to the weather


Project Details

Client: PGAL, for the Metropolitan Washington Airports Authority (MWAA)

Location: Arlington, Virginia

Market: Aviation

Project Category: Roofing

REI Role: Subconsultant (Building Enclosure Engineer of Record)

Design: Original design: October 2019; Code update and permit set: March 2026

Construction: Being rebid; construction anticipated to start Spring 2027

System(s): TPO roofing over two layers of polyiso insulation and coverboard (R-30); polyethylene vapor retarder at metal-deck upper roofs

Owner Requirements: MWAA design standards and Building Codes review; MWAA Contract DCA-12125004, Task One

Services: Roof Condition Assessment • Roof Replacement Design • Code Analysis • Submittal Review • Construction Administration