North Stafford High School Roof Replacement and Facade Renovation

A building-wide envelope renovation in two parts: replacement of 275,000 square feet of single-ply roofing with a reflective built-up roof, completed in 2016, followed by replacement of the split-faced CMU facade with insulated metal wall panels and new windows and storefronts.

North Stafford High School Roof Replacement and Facade Renovation

Overview

For Stafford County Public Schools, REI split the building-wide envelope renovation of North Stafford High School into two projects. For the roof, REI investigated the existing single-ply systems with test cuts and designed the replacement of 275,000 square feet of membrane with a 3-ply asphalt and fiberglass built-up roof with a reflective mineral-surfaced cap sheet over tapered insulation, along with expansion joint, flashing and drainage improvements; the roof was completed in 2016 and substantially completed on time. For the facade, REI investigated the split-faced CMU veneer and original windows and designed their replacement with prefinished Galvalume decorative wall panels on new light-gauge framing with spray foam insulation, plus new windows, storefronts and doors and brick masonry repairs. The facade work is being built in two phases, with REI administering construction.


Scope of Work

  • Investigated the roofs and observed investigative test cuts to determine existing construction

  • Designed replacement of 275,000 square feet of single-ply membrane with a 3-ply asphalt and fiberglass built-up roof with reflective mineral-surfaced cap sheet over tapered insulation on the existing steel deck

  • Detailed tapered insulation layouts, expansion joint replacement, perimeter and through-wall flashing, divider curb modifications, extensive drainage modifications and isolated concrete walkway slab repairs

  • Investigated the facade and windows, including test cuts into the split-faced CMU veneer

  • Designed removal of the split-faced CMU veneer down to the existing CMU and steel beams and new prefinished Galvalume decorative wall panels on light-gauge framing secured with clips, with spray foam insulation and flashings

  • Designed replacement of the original metal-framed windows, storefronts and doors, and repairs to the brick masonry veneer

  • Prepared specifications, assisted with bidding, and provided contract administration for the roof and facade work


Results

  • Roof replacement substantially completed on time in 2016

  • New spray foam insulation behind the metal panels improves the building's thermal performance


Project Details

Client: Stafford County Public Schools

Location: Stafford, Virginia

Market: K-12 Education

Project Category: Facade

REI Role: Prime Consultant

Roof Replacement Completed: 2016

Facade Renovation: Ongoing — Phase I (facade) in construction; Phase II (windows, storefront and doors) to follow

Area / Quantity: 275,000 SF of roofing

System(s): Roof: 3-ply asphalt and fiberglass built-up roofing with reflective mineral-surfaced (SBS modified) cap sheet over tapered polyisocyanurate insulation on existing steel deck; Facade: prefinished Galvalume decorative wall panels on light-gauge metal framing with spray foam insulation; replacement windows, storefronts and doors

Phases: Roof replacement (completed 2016); Facade Phase I: wall panel replacement; Facade Phase II: window, storefront and door replacement

Location: 839 Garrisonville Road, Stafford, Virginia

Services: Roof Condition Assessment • Facade Condition Assessment • Window Condition Assessment • Roof Replacement Design • Facade Restoration Design • Masonry Restoration Design • Bidding Assistance • Construction Administration