National Archives II Roof Replacement Consulting

Roof consulting and structural engineering through several phases of replacing the inverted (protected membrane) roofs with fully adhered TPO roofing, including a new photovoltaic array, at the National Archives II facility.

National Archives II Roof Replacement Consulting

Overview

Over several phases between 2012 and 2018, REI provided third-party roof consulting and structural engineering for the replacement of the protected membrane (inverted) roofs at the National Archives II facility in College Park, Maryland. The original roofs consist of a hot-applied rubberized asphalt membrane on the concrete deck, covered by extruded polystyrene insulation and stone ballast. In each phase the stone ballast and insulation were removed and new insulation and a white TPO membrane were fully adhered over the existing membrane, which was left in place as an additional layer of protection.

REI worked on the construction team with general contractor Grunley Construction and roofing contractor The James Myers Company, serving as the independent roofing consultant required by the National Archives and Records Administration (NARA) and observing the work from submittal review through final inspection.


Roof Replacement and Photovoltaic Array (2012–2013)

  • Reviewed shop drawings and observed the replacement of the low, penthouse and upper roofs with adhered polyisocyanurate insulation, a high-density cover board and TPO roofing

  • Analyzed the roof structure for the new ballasted photovoltaic array, confirming that removing the stone ballast left capacity for the array, and checked temporary loading from stored insulation

  • Recommended electronic leak detection of the existing membrane before it was covered, and addressed expansion joint covers, lightning protection penetrations, counterflashing at existing reglets, ponding at drains and adhesive odors at air intakes

  • Issued observation reports and performed the punch list inspection with the roofing manufacturer


Phase II Roof Replacement (2013)

  • Observed adhesion pull tests on the exposed original membrane and the repair of unbonded or split membrane and base flashing before new insulation and TPO roofing were installed

  • Evaluated slab cracking in rooms below the roof, found no structural distress requiring immediate repair, and recommended crack monitoring and anchor repairs for light fixture hangers


Sections 7 and 9 Roof Replacement (2017–2018)

  • Reviewed roofing submittals for approximately 44,000 square feet of new roofing on two roof sections: polyisocyanurate insulation and a high-density cover board set in foam adhesive ribbons over the existing membrane, and fully adhered 80-mil TPO membrane

  • Observed and interpreted adhesion pull tests of insulation samples on each roof; all results far exceeded the design wind uplift pressures, and REI had soft or wet areas of the old membrane removed before insulation was installed

  • Made periodic site observations with observation reports, resolving adhesive mixing problems, odor control at air intakes, tapered drain sumps and counterflashing details with the contractor

  • Performed the punch list inspection and a final inspection after completion of outstanding work


Project Details

Client: Grunley Construction Co., Inc. and The James Myers Company, Inc., for the National Archives and Records Administration (NARA)

Location: College Park, Maryland

Market: Government

Project Category: Roofing

REI Role: Independent roofing consultant and structural engineer to the contractor team

Years: 2012–2018

System(s): Existing: protected membrane roofing (rubberized asphalt membrane with extruded polystyrene insulation and stone ballast or pavers). New: polyisocyanurate insulation and high-density cover board adhered over the existing membrane, with fully adhered TPO roof membrane; ballasted photovoltaic array

Roofing Contractor: The James Myers Company, Inc. (subcontractor to Grunley Construction)

Services: Submittal Review • Construction Administration • Adhesion Testing Observation • Structural Load Analysis • Punch List and Final Inspections