International Monetary Fund Headquarters Roof, Skylight and Terrace Rehabilitation
Condition assessment of every roof and skylight on the International Monetary Fund's two 14-story Washington headquarters buildings, followed by design and construction administration of a multi-year program of roof, skylight, terrace and green roof work.

Overview
REI assessed the roofing and skylight systems on the IMF's headquarters complex in downtown Washington: HQ1, built in three phases between 1971 and 1995, and HQ2, completed in 2005. Using a leak survey, test cuts, an infrared moisture survey and structural capacity checks, REI's 2009 report gave the Fund the condition, remaining life and replacement recommendations for each roof and skylight, with cost estimates and sustainability options. REI then prepared bid documents for two fiscal-year packages and administered construction from late 2010 into 2012, with the building fully occupied.
Scope of Work
Surveyed every roof and skylight on both buildings with a leak survey, test cuts, an infrared moisture survey and archived drawing review
Checked roof deck structural capacity for paver ballast and extensive green roof overburden
Prepared a condition assessment report with summary tables of age, life expectancy, replacement recommendations and cost estimates, including green roof, high-reflectance and photovoltaic options
Designed protected membrane roof assemblies using hot-applied rubberized asphalt waterproofing, including overflow drainage
Designed new built-in gutter liners, sealant and gasket replacement, and new aluminum catwalks and access ladders at the HQ1 main atrium skylight
Designed replacement of the 5th Floor Terrace waterproofing, including removal and reinstallation of granite paving, topping slab and garden plantings
Designed an extensive green roof retrofit and perimeter flashing repairs on HQ2, and replacement of the HQ1 cooling tower roof
Provided construction administration through 61 observation reports, including RFI responses, submittal reviews and punch lists
Results
Gave the Fund a phased, prioritized plan covering every roof and skylight, so replacements could be budgeted by fiscal year
Converted the HQ2 roof to an extensive green roof while keeping the existing membrane warranty, by following the manufacturer's requirements
Kept the fully occupied headquarters in operation, with terrace work performed at night and materials stored off site
When construction uncovered drainage problems over an electrical transformer vault, REI developed options with the Fund, the utility and the contractor
Project Details
Client: International Monetary Fund
Location: Washington, D.C.
Market: Government
Project Category: Roofing / Waterproofing
REI Role: Subconsultant to OPX (Building Envelope Engineer)
Design: Condition assessment report: November 2009; Bid documents (FY2011 and FY2012): July 2010
Area / Quantity: two 14-story buildings
System(s): Hot-applied rubberized asphalt protected membrane roofing; extensive vegetated roof; built-in skylight gutter liners; aluminum catwalks; plaza waterproofing under granite paving
Buildings: HQ1: 700 19th Street NW (Phases I–III, 1971, 1983, 1995); HQ2: completed 2005
Services: Roof Condition Assessment • Infrared Roof Survey • Roof Replacement Design • Skylight Restoration Design • Waterproofing Design • Bidding Assistance • Submittal Review • Construction Administration