Chopticon High School Roof Replacement, Structural Modifications and Facade Repairs
Building envelope and structural engineering for a building-wide school renovation: replacement of about 150,200 square feet of built-up roofing, structural dunnage and joist reinforcement for new rooftop equipment, and facade repairs.

Overview
As the building envelope and structural engineering consultant on WGM Architects' team for a building-wide renovation of Chopticon High School, REI designed a replacement roofing system, structural modifications for new rooftop units, and miscellaneous facade repairs. The school has been expanded several times, leaving various substrates and many complex transitions and expansion joints across the roof and facade, so REI carried out an extensive field investigation with investigative test cuts and detailed measurements. REI designed replacement of approximately 150,200 square feet of built-up roofing with a new 3-ply asphalt and fiberglass hybrid built-up roof with a reflective mineral-surfaced cap sheet over tapered and flat insulation on the existing steel and gypsum decks. Working with the MEP engineer, REI designed new steel dunnage, joist reinforcement and service platforms for new rooftop equipment, and deck patching where units were removed.
Scope of Work
Performed an extensive field investigation, observing test cuts and taking detailed measurements to verify existing conditions
Designed replacement of approximately 150,200 square feet of built-up roofing with a new 3-ply asphalt and fiberglass hybrid built-up roof with a reflective mineral-surfaced cap sheet over tapered and flat insulation
Prepared roof plans showing deck slopes, drains, crickets, divider curbs, expansion joints and new and existing rooftop equipment, with expansion joint details including isometrics of complex transitions
Designed structural steel dunnage for new and replaced rooftop units, reinforcement of existing steel bar joists, and service platforms with access ladders, guards and bar grating
Detailed deck patching where rooftop equipment was removed, coordinated with the MEP engineer
Designed facade repairs: resealing control joints, replacing vertical expansion joints, elastomeric coating of exposed concrete columns and beams, soffit replacement, and removal and reinstallation of lettering and signage
Assisted with bidding and is providing construction administration, including submittal and payment reviews, site visits and clarifications
Project Details
Client: St. Mary's County Public Schools, through WGM Architects
Location: Morganza, Maryland
Market: K-12 Education
Project Category: Roofing
REI Role: Subconsultant to WGM Architects
Status: Ongoing — construction administration in progress
Area / Quantity: Approximately 150,200 SF of roofing
System(s): 3-ply asphalt and fiberglass built-up roof with reflective mineral-surfaced cap sheet (hybrid system) over tapered and flat insulation on existing steel and gypsum roof decks; structural steel dunnage and service platforms
Location: 25390 Colton Point Road, Morganza, Maryland
Services: Roof Condition Assessment • Facade Condition Assessment • Roof Replacement Design • Structural Dunnage Design • Structural Repair Design • Facade Restoration Design • Bidding Assistance • Submittal Review • Construction Administration