Calvert Elementary School Partial Roof Replacement Design

Roofing consultant for a building-wide school renovation: investigation and design to replace about 17,200 square feet of built-up roofing with a TPO roofing system, coordinated with new rooftop mechanical equipment.

Calvert Elementary School Partial Roof Replacement Design

Overview

REI served as roofing consultant on the project team for a building-wide renovation of Calvert Elementary School. After a field investigation and observation of test cuts, REI designed the replacement of approximately 17,200 square feet of built-up roofing with a 60-mil thermoplastic polyolefin (TPO) roofing system over tapered and flat insulation on the existing steel and gypsum decks. REI worked closely with the project's MEP engineer to locate new rooftop equipment and prepared flashing tie-in details for the new penetrations. Because of budget constraints, only the roof above the mechanical penthouse was replaced, along with the tie-in work at the new equipment.


Scope of Work

  • Performed a field investigation and observed investigative test cuts to determine existing construction

  • Designed replacement of about 17,200 square feet of built-up roofing with a 60-mil TPO roofing system over tapered and flat insulation

  • Detailed expansion joint replacement, perimeter and through-wall flashings, roof drain replacement, and a modified gravel stop termination at wall expansion joints

  • Coordinated new rooftop equipment locations with the MEP engineer and prepared flashing tie-in details for the new penetrations

  • Prepared technical specifications for the new roofing system and flashings


Results

  • Due to budget constraints, the roof above the mechanical penthouse was replaced and the new equipment was tied in to the existing roofing; the remaining roof design is available for a future phase


Project Details

Client: Calvert County Public Schools

Location: Prince Frederick, Maryland

Market: K-12 Education

Project Category: Roofing

REI Role: Subconsultant to WGM Architects

Design: 2024

Construction: Partial (roof above the mechanical penthouse and new equipment tie-ins)

Area: Approximately 17,200 square feet designed (partial replacement built)

System(s): 60-mil thermoplastic polyolefin (TPO) single-ply roofing over tapered and flat insulation

Roof Decks: Existing steel and gypsum decks

Services: Roof Condition Assessment • Roof Replacement Design