Auburn Village Condominium Slate Roof Replacement

Leak survey, slate roof replacement design and construction administration for all seven buildings of a garden-style condominium community in Alexandria, completed in two phases while residents remained in their homes.

Auburn Village Condominium Slate Roof Replacement

Overview

REI was retained by the Auburn Village Condominium Unit Owners Association to investigate leaks and design the replacement of the slate roofs on all seven of the community's brick buildings along East Glebe Road, Ashby Street, Commonwealth Avenue and Auburn Court. After a 2016 leak survey, REI prepared bid documents with four roofing options and three phasing options so the Board could weigh cost, appearance and service life. On REI's recommendation, the Board chose all-new slate, and REI administered construction through completion in 2019.


Scope of Work

  • Surveyed roof leaks and conditions in 2016, including the slate, flashings, dormers, plank roof deck and attic framing

  • Prepared bid documents with four base bids (recycled slate, new slate, synthetic slate, and asphalt shingles over a new ventilated deck) and one-, two- and three-phase pricing

  • Designed new slate roofing over sheet membrane underlayment, with repairs to the existing plank roof deck

  • Specified new eave, rake, valley and ridge flashings, new wood and PVC fascia, and 6-inch seamless aluminum gutters and downspouts

  • Replaced the original wood-framed dormers with prefabricated, louvered half-round copper dormers

  • Coordinated relocation of exterior lighting and cable lines mounted on the old fascia

  • Evaluated the bids, recommended the roofing system and contractor, and prepared the owner–contractor agreement

  • Provided construction administration over two phases, including observation, submittal reviews, change orders and 31 payment reviews


Results

  • Recommended new slate after the bids showed recycling the existing slate would save less than 4 percent, since the labor to salvage it offset the material savings

  • Advised against asphalt shingles, with a 20 to 25 year life, in favor of slate that can provide 100+ years of service and preserves the community's character

  • Structured the contract so the Board could start the second phase immediately after the first, earning a 2 percent credit from the contractor

  • Final contract amount came in about 3 percent below the original contract sum


Project Details

Client: Auburn Village Condominium Unit Owners Association

Location: Alexandria, Virginia

Market: Multifamily / Condominium

Project Category: Roofing

REI Role: Prime Consultant

Design Completed: November 2016

Area / Quantity: 7 buildings

System(s): Natural slate roofing over sheet membrane underlayment; copper half-round louvered dormers; sheet metal flashings; seamless aluminum gutters

Phases: Phase I: Buildings 1 and 2; Phase II: Buildings 3 through 7

Services: Roof Condition Assessment • Roof Replacement Design • Bidding Assistance • Construction Administration